Select a language:



Omsk polypropylene plant increases the safety standards


30 November 2017

The best practices of the contractors in the field of labor protection and industrial safety were evaluated at Omsk polypropylene plant. Three companies will be awarded for the safe operation during the shutdown maintenance at the enterprise.

19 contractors were involved in repair work at the joint venture of GC "Titan", SIBUR, "Gazprom-Neft". Every day up to 350 people were at the site including "Poliom" personnel.

There was established the committee to evaluate the work of contractors. This committee included the General Director of "Poliom" Ltd., the chief technical specialists, the heads of the production workshops and the head of HSE department.

The final evaluation of each contractor was calculated using a special formula. According to the results of condition examination of labor protection and industrial safety, the brigade of "RMZ "Gazprom-Neft-Omsk Oil Refinery Plant" took the first place by a long shot, the second place was taken by one of three brigades of "Energoremservis" Ltd, which replaced the heat exchanger in the department of propane-propylene fraction processing, the brigade of "Energoperspectiva" Ltd. closed top three "safe" brigades.

It should be noted that the plant has chosen a nominal award format: the award will be given to members of a particular brigade, but not to the entire organization. The award ceremony will be held at "Poliom"Ltd. today, on 1 December.

Omsk polypropylene plant introduced the practice of contractors evaluating in the field of labor protection and industrial safety last year. Nine people were first awarded according to the results of the shutdown maintenance in autumn of 2016.

Summary:

The shutdown maintenance at the plant "Poliom" began on 23 October, 2017, and was lasting 14 days. In accordance with the plan, the main works included: the replacement of two heat exchangers in the polypropylene production workshop and in the department of propane-propylene fraction processing, overhaul of the large compressor unit, carrying out the advanced tie-in to technological pipelines as part of the projects on polishing refining and installation of hydrocarbon gases compressing unit PK-503. 




Back to the list
Contact Information:
Phones: +7 (3812) 29-95-55, 35-69-31
Fax: +7 (3812) 35-69-32
Е-mail: info@titan-omsk.ru
Address: 644035, Russia, Omsk 22, Gubkin str.
Select a language:
©2012 Group of Companies «Titan»
All rights reserved